ACS's CIMIC In JV With John Holland And Ghella To Deliver Sydney Metro West - Eastern Tunnelling Package
CIMIC Group Limited:
SAID ON TUESDAY ITS CONSTRUCTION COMPANY CPB CONTRACTORS, IN JOINT VENTURE WITH JOHN HOLLAND AND GHELLA, WAS SELECTED TO DELIVER SYDNEY METRO WEST – EASTERN TUNNELLING PACKAGE
CPB CONTRACTORS IS 40% JOINT VENTURE PARTNER DELIVERING $1.63 BILLION (1.58 BILLION EUROS) PROJECT
CONSTRUCTION WILL COMMENCE IN 2023 AND IS SCHEDULED FOR COMPLETION IN 2025
SYDNEY METRO WEST WILL DELIVER NEW UNDERGROUND RAIL CONNECTION BETWEEN THE CBDS OF PARRAMATTA AND SYDNEY
WORKS TO BE DELIVERED UNDER EASTERN TUNNELLING PACKAGE INCLUDE 3.5 KILOMETRES OF METRO TUNNELS BETWEEN FUTURE STATIONS AT THE BAYS AND HUNTER STREET IN SYDNEY’S CBD AND EXCAVATION OF CAVERNS AND SHAFTS AT PYRMONT AND HUNTER STREET STATIONS
Source text: https://bit.ly/3XGlMuK
Further company coverage:
(1 euro = $1.0341)